Late payment to a micro or small supplier costs interest, a delayed tax deduction and public disclosure. How the deadline works and how to manage it.

Stretching supplier payments is the oldest way to fund a business. When the supplier is a micro or small enterprise, the law turns that habit into the most expensive credit a company can use. The interest rate is fixed by statute, the tax deduction moves to a later year, and the overdue amount is reported in public filings. Most finance teams know the phrase "45 days". Fewer know that the real deadline is often 15.

What the law requires

Who is protected. The rule protects a supplier that is a micro or small enterprise. The buyer's own size does not matter.

CategoryInvestment in plant and equipmentTurnover
MicroUp to ₹2.5 croreUp to ₹10 crore
SmallUp to ₹25 croreUp to ₹100 crore

Medium enterprises are not covered by the payment rule.

The deadline. Section 15 of the MSMED Act sets it.

SituationPay by
No written agreement on payment terms15 days from acceptance
Written agreementThe agreed date, but never later than 45 days from acceptance

When the clock starts. It starts on acceptance, which normally means the day the goods are delivered or the service is rendered. If the buyer objects in writing within 15 days of delivery, the clock starts on the day the supplier removes the objection. If the buyer says nothing in writing for 15 days, the supply is treated as accepted on delivery.

What paying late costs

All four consequences below come from the law itself.

  1. Interest at a rate you cannot negotiate. From the day after the deadline, the buyer owes compound interest, calculated monthly, at three times the bank rate notified by the Reserve Bank of India. Section 16 applies whatever the contract says, so a clause waiving or capping interest does not help.
  2. No tax deduction for that interest. Section 23 bars the buyer from deducting it when computing taxable income.
  3. A delayed deduction for the purchase itself. Under Section 37(2)(g) of the Income-tax Act, 2025, an amount paid to a micro or small enterprise after the Section 15 deadline is deductible only in the year it is actually paid. For most other dues of this kind, paying before the return filing date saves the deduction. That relief does not apply here. A bill that is overdue and unpaid on 31 March moves its deduction to the next year, and the company pays tax this year on profit it did not really make.
  4. Disclosure, and a hard road in a dispute. A buyer's audited accounts must show the unpaid principal and interest owed to these suppliers. A company must also file Form MSME-1 with the Registrar every half year, by 31 October and 30 April, for amounts outstanding beyond 45 days. Failure draws a penalty of ₹20,000, plus ₹1,000 a day, up to ₹3 lakh, on the company and on each officer in default. If the supplier takes the matter to the Facilitation Council and wins, the buyer must deposit 75 per cent of the award before a court will hear a challenge.

Where companies get it wrong

"Our terms are 60 days." The law caps a written term at 45 days, so the days beyond 45 do not count. Interest and the tax rule both run from day 45.

"We have 45 days." Only with a written agreement. A purchase made on a phone call or an invoice with no agreed terms falls under the 15-day rule.

Counting from the invoice or from internal approval. The clock runs from delivery. Time spent on goods inspection, invoice matching or waiting for a signature does not stop it. Only a written objection within 15 days does.

Treating every "MSME" vendor the same. Three groups look alike on a vendor list but are treated differently. Medium enterprises are outside the rule. Wholesale and retail traders can register on the Udyam portal, but the Ministry's 2021 memorandum limits their benefit to priority sector lending, and a later clarification says they do not get the delayed-payment protection. Micro and small manufacturers and service providers are fully covered. The supplier's Udyam certificate shows both its category and its activity.

Assuming registration date does not matter. It may. The Supreme Court held in 2021 that a supplier could not claim the Act's benefits for supplies made before it registered. A later bench took a different view on one aspect and referred the question to a larger bench. Until that is settled, the buyer's safest record is the supplier's certificate as it stood on the date of supply.

Worrying about the wrong bills at year-end. For the tax rule, only bills that are both past their deadline and unpaid on 31 March are affected. A bill delivered in late March that is still within its 15 or 45 days is not.

Good practiceA process for the finance team

This section is professional judgement, not a legal requirement.

  1. Tag every vendor. Record in the vendor master whether each supplier is micro, small, medium, a trader or unregistered, with its Udyam number and the certificate date. Ask for a fresh certificate every year, because a supplier's category can change.
  2. Put terms in writing for every micro and small supplier. A one-line payment term in the purchase order turns a 15-day deadline into the agreed period, up to 45 days.
  3. Compute the due date from delivery. Set the accounting system to calculate it from the goods receipt or service completion date, not from the date the invoice was booked.
  4. Raise quality disputes in writing, within 15 days. An objection made on a call does not move the deadline.
  5. Watch one report. Run a weekly list of micro and small supplier bills sorted by days left to the deadline. Run it again before the March close.
  6. Compare the cost of money. Before delaying a payment, compare three times the bank rate, compounded monthly and not deductible, with the cost of drawing on the company's bank limit. The bank is usually far cheaper.
  7. Make late payment a decision. If a micro or small supplier is to be paid late, someone senior should approve it with the interest and tax cost in front of them.

Frequently asked questions

We paid late, but within the same financial year. Do we lose the deduction?

No. The deduction is allowed in the year of actual payment, so a bill paid late but before 31 March is deducted in that same year. The interest under Section 16 is still owed.

The supplier has agreed in writing not to charge interest. Is that enough?

No. Section 16 applies despite anything in an agreement between buyer and supplier.

Which law applies to bills from the financial year 2025-26?

Section 43B(h) of the Income-tax Act, 1961. Section 37(2)(g) of the 2025 Act applies from 1 April 2026. The rule is the same under both.

This article is for general information and is not professional advice.